Location
St. Louis, Missouri
Presentation Date
06 Apr 1995, 10:30 am - 12:30 pm
Abstract
Very poor ground conditions and soils that were susceptible to liquefaction to depths of up to 20m beneath the site were major problems for the construction of the largest natural gas processing terminal in Europe. An innovative foundation solution combining deep vibro compaction with short cast in place piles driven into the treated soils was adopted as both cost and programme effective. The Design and Build project also included advance civils work comprising earthworks, drainage and road construction. The contract started in September 1991 and was completed by October 1992, with the process plant programmed to be on-stream by October 1994. This paper describes the seismic aspects of the foundation solution.
Department(s)
Civil, Architectural and Environmental Engineering
Meeting Name
3rd International Conference on Recent Advances in Geotechnical Earthquake Engineering and Soil Dynamics
Publisher
University of Missouri--Rolla
Document Version
Final Version
Rights
© 1995 University of Missouri--Rolla, All rights reserved.
Creative Commons Licensing
This work is licensed under a Creative Commons Attribution-Noncommercial-No Derivative Works 4.0 License.
Document Type
Article - Conference proceedings
File Type
text
Language
English
Recommended Citation
Raison, C. A.; Slocombe, B. C.; Bell, A. L.; and Baez, J. I., "North Morecambe Terminal, Barrow, Ground Stabilisation and Pile Foundations" (1995). International Conferences on Recent Advances in Geotechnical Earthquake Engineering and Soil Dynamics. 2.
https://scholarsmine.mst.edu/icrageesd/03icrageesd/session03/2
Included in
North Morecambe Terminal, Barrow, Ground Stabilisation and Pile Foundations
St. Louis, Missouri
Very poor ground conditions and soils that were susceptible to liquefaction to depths of up to 20m beneath the site were major problems for the construction of the largest natural gas processing terminal in Europe. An innovative foundation solution combining deep vibro compaction with short cast in place piles driven into the treated soils was adopted as both cost and programme effective. The Design and Build project also included advance civils work comprising earthworks, drainage and road construction. The contract started in September 1991 and was completed by October 1992, with the process plant programmed to be on-stream by October 1994. This paper describes the seismic aspects of the foundation solution.