Abstract

The objective of the study was to record and evaluate ground vibration and noise generated during the installation of rammed aggregate piers (RAPs). Summarized are ground vibration and noise induced by the ramming equipment (i.e. the hydraulic break hammer and rammer) during the installation of forty-five RAPs at a single site. Data were collected during the entire installation process for each pier, which allowed for the measurement of ground vibration and noise levels for periods when the ramming equipment was positioned at different depths within the RAP. Measurements were also taken at different horizontal distances from the ramming equipment and RAP being installed. The entire data set consists of over 160 ground vibration measurements and over 260 noise measurements. Peak ground velocities measured during the study ranged between approximately 0.5 and 15 millimeters per second for horizontal distances ranging between 1.5 and 10.5 meters. Corresponding vibration frequencies ranged between approximately 20 and 60 Hz. Measured noise levels ranged between approximately 82 and 111 dBA for measurement locations between approximately 1.5 and 10.5 meters from the hammer. Overall, these measured ground vibrations and noise levels are moderate in nature and below those typically generated during pile driving.

Department(s)

Civil, Architectural and Environmental Engineering

Meeting Name

6th Conference of the International Conference on Case Histories in Geotechnical Engineering

Publisher

Missouri University of Science and Technology

Document Version

Final Version

Rights

© 2008 Missouri University of Science and Technology, All rights reserved.

Creative Commons Licensing

Creative Commons License
This work is licensed under a Creative Commons Attribution-Noncommercial-No Derivative Works 4.0 License.

Document Type

Article - Conference proceedings

File Type

text

Language

English

Share

 
COinS
 
Aug 11th, 12:00 AM Aug 16th, 12:00 AM

Measurement of Vibration and Noise During the Installation of Rammed Aggregate Piers

Arlington, Virginia

The objective of the study was to record and evaluate ground vibration and noise generated during the installation of rammed aggregate piers (RAPs). Summarized are ground vibration and noise induced by the ramming equipment (i.e. the hydraulic break hammer and rammer) during the installation of forty-five RAPs at a single site. Data were collected during the entire installation process for each pier, which allowed for the measurement of ground vibration and noise levels for periods when the ramming equipment was positioned at different depths within the RAP. Measurements were also taken at different horizontal distances from the ramming equipment and RAP being installed. The entire data set consists of over 160 ground vibration measurements and over 260 noise measurements. Peak ground velocities measured during the study ranged between approximately 0.5 and 15 millimeters per second for horizontal distances ranging between 1.5 and 10.5 meters. Corresponding vibration frequencies ranged between approximately 20 and 60 Hz. Measured noise levels ranged between approximately 82 and 111 dBA for measurement locations between approximately 1.5 and 10.5 meters from the hammer. Overall, these measured ground vibrations and noise levels are moderate in nature and below those typically generated during pile driving.