Location

New York, New York

Date

16 Apr 2004, 8:00am - 9:30am

Abstract

A new railway line was under construction in North-eastern Sweden, along the shoreline of the Gulf of Bothnia. The terrain consisted of Postglacial clay and silt valleys, and ridges of Precambrian bedrock, crossing the railway line. The railway level was about 20m below the ground surface. For the design of freezing, a freezing analysis was carried out to determine the pipeline depths and distances, to estimate the necessary time for freezing and to determine temperatures within the frozen zone. To estimate the deformations, displacements and safety level, a mechanical analysis of the tunnel cross-section was carried out. As input, the geometry of the soil layers, bedrock and temperature zones was given. Time- and temperature-dependent mechanical parameters were estimated for different soils and temperatures. The analysis was carried out for 12 phases simulating different phases during tunnelling. The estimated displacements for the tunnel arch were negligible, if the temperatures were at or below -15°C. The freezing was started in May 2002, and completed in September 2002. The tunnelling was started in September, and it was completed in November 2002, following with the casting of final liner. According to the experiences until now, the work has progressed successfully.

Department(s)

Civil, Architectural and Environmental Engineering

Meeting Name

5th Conference of the International Conference on Case Histories in Geotechnical Engineering

Publisher

University of Missouri--Rolla

Document Version

Final Version

Rights

© 2004 University of Missouri--Rolla, All rights reserved.

Creative Commons Licensing

Creative Commons License
This work is licensed under a Creative Commons Attribution-Noncommercial-No Derivative Works 4.0 License.

Document Type

Article - Conference proceedings

File Type

text

Language

English

Share

 
COinS
 
Apr 13th, 12:00 AM Apr 17th, 12:00 AM

Railway Tunnelling in Frozen Ground on Bothniabana

New York, New York

A new railway line was under construction in North-eastern Sweden, along the shoreline of the Gulf of Bothnia. The terrain consisted of Postglacial clay and silt valleys, and ridges of Precambrian bedrock, crossing the railway line. The railway level was about 20m below the ground surface. For the design of freezing, a freezing analysis was carried out to determine the pipeline depths and distances, to estimate the necessary time for freezing and to determine temperatures within the frozen zone. To estimate the deformations, displacements and safety level, a mechanical analysis of the tunnel cross-section was carried out. As input, the geometry of the soil layers, bedrock and temperature zones was given. Time- and temperature-dependent mechanical parameters were estimated for different soils and temperatures. The analysis was carried out for 12 phases simulating different phases during tunnelling. The estimated displacements for the tunnel arch were negligible, if the temperatures were at or below -15°C. The freezing was started in May 2002, and completed in September 2002. The tunnelling was started in September, and it was completed in November 2002, following with the casting of final liner. According to the experiences until now, the work has progressed successfully.