Abstract

Masjed-e-Soleiman Dam and Hydroelectric Power plant (170 high rock fill dam with capacity of 2000 MW) is located about 25 Km. to the north east of Masjed-e-Soleiman (Southwestern Iran) on Karun river. The powerhouse cavern is an underground structure, consisting of eight 250 MW power units (4 units each for phase 1 and extension phase). Overburden of powerhouse is 250-320 meters. The first step of project (that is a Dam with supply 1000 MW electricity), has been completed recently. In order to ensure the stability of roof of the extension p.h. cavern, dywidag brand monobars (15 or 20 m. long) with working load of 624 KN have been used. In this paper, the geological condition , rock support measures and the method statement of opening and sequences of excavation for the extension powerhouse cavern, analysis the impact of installation of monobars on cavern roof stability (on the basis of the instrumentation results) have been discussed briefly.

Department(s)

Civil, Architectural and Environmental Engineering

Meeting Name

5th Conference of the International Conference on Case Histories in Geotechnical Engineering

Publisher

University of Missouri--Rolla

Document Version

Final Version

Rights

© 2004 University of Missouri--Rolla, All rights reserved.

Creative Commons Licensing

Creative Commons License
This work is licensed under a Creative Commons Attribution-Noncommercial-No Derivative Works 4.0 License.

Document Type

Article - Conference proceedings

File Type

text

Language

English

Share

 
COinS
 
Apr 13th, 12:00 AM Apr 17th, 12:00 AM

Effect of Installing Monobars in Stability of Powerhouse Cavern Roof in Masjed - Soleiman Power Plant Extension

New York, New York

Masjed-e-Soleiman Dam and Hydroelectric Power plant (170 high rock fill dam with capacity of 2000 MW) is located about 25 Km. to the north east of Masjed-e-Soleiman (Southwestern Iran) on Karun river. The powerhouse cavern is an underground structure, consisting of eight 250 MW power units (4 units each for phase 1 and extension phase). Overburden of powerhouse is 250-320 meters. The first step of project (that is a Dam with supply 1000 MW electricity), has been completed recently. In order to ensure the stability of roof of the extension p.h. cavern, dywidag brand monobars (15 or 20 m. long) with working load of 624 KN have been used. In this paper, the geological condition , rock support measures and the method statement of opening and sequences of excavation for the extension powerhouse cavern, analysis the impact of installation of monobars on cavern roof stability (on the basis of the instrumentation results) have been discussed briefly.