Location

New York, New York

Date

14 Apr 2004, 4:30 pm - 6:30 pm

Abstract

The construction of the deepest base grouted piles in London was a challenge in itself, but to do this in a city center site measuring 85m by 53m in plan and 3.5m below street level was a true achievement. The piled foundations had been designed to isolate the building from future ground movements associated with construction of the CrossRail underground rail tunnels linking east and west London, which would run below the building. To achieve the required isolation, the design of the foundations called for the provision of frictionless pile sleeves to depths of 26m (85ft), and base grouting of the piles - to limit settlement to 20mm (4/5in). 54No. base-grouted piles were installed through London Clay into dense Thanet Sand, to depths of 57m (190ft). This paper describes the construction phase of the work, in particular the processes and methods used to construct the load bearing piles and the removal of obstructions, including coring through existing reinforced concrete piles. Also described is the planning and preparation of the contract and the methods undertaken to overcome the space and environmental constraints.

Department(s)

Civil, Architectural and Environmental Engineering

Meeting Name

5th Conference of the International Conference on Case Histories in Geotechnical Engineering

Publisher

University of Missouri--Rolla

Document Version

Final Version

Rights

© 2004 University of Missouri--Rolla, All rights reserved.

Creative Commons Licensing

Creative Commons License
This work is licensed under a Creative Commons Attribution-Noncommercial-No Derivative Works 4.0 License.

Document Type

Article - Conference proceedings

File Type

text

Language

English

Share

 
COinS
 
Apr 13th, 12:00 AM Apr 17th, 12:00 AM

Moorhouse Development – London Deep Sleeved Base-Grouted Piles and Perimeter Retaining Walls

New York, New York

The construction of the deepest base grouted piles in London was a challenge in itself, but to do this in a city center site measuring 85m by 53m in plan and 3.5m below street level was a true achievement. The piled foundations had been designed to isolate the building from future ground movements associated with construction of the CrossRail underground rail tunnels linking east and west London, which would run below the building. To achieve the required isolation, the design of the foundations called for the provision of frictionless pile sleeves to depths of 26m (85ft), and base grouting of the piles - to limit settlement to 20mm (4/5in). 54No. base-grouted piles were installed through London Clay into dense Thanet Sand, to depths of 57m (190ft). This paper describes the construction phase of the work, in particular the processes and methods used to construct the load bearing piles and the removal of obstructions, including coring through existing reinforced concrete piles. Also described is the planning and preparation of the contract and the methods undertaken to overcome the space and environmental constraints.