Location
New York, New York
Date
14 Apr 2004, 4:30 pm - 6:30 pm
Abstract
The replacement of a steam generator at a nuclear power plant was accomplished with the use of a massive crane, believed to be one of the largest available cranes in the world market. Four steam generators were replaced, with each generator weighing 3.2 MN. The crane used for the job had a circular support that required a ring foundation. The crane support imposed huge loads on the ring foundation. Because of the presence of soft to medium stiff clayey fill on one side of the ring foundation, the load-sensitive nature of existing underground safetyrelated duct banks, and the nature of the loads applied to the foundation, it was necessary to support the ring foundation on piles. In order to minimize vibrations next to the containment building (the plant was operational while the piles were being installed), micropiles were selected. A total of 80 micropiles were installed, most of them at a batter of 10o from vertical, to provide the required vertical and lateral load resistance. Despite significant challenges imposed by space constraints, subsurface conditions, buried utilities, and design changes, the micropiles were installed within schedule, and performed as designed.
Department(s)
Civil, Architectural and Environmental Engineering
Meeting Name
5th Conference of the International Conference on Case Histories in Geotechnical Engineering
Publisher
University of Missouri--Rolla
Document Version
Final Version
Rights
© 2004 University of Missouri--Rolla, All rights reserved.
Creative Commons Licensing
This work is licensed under a Creative Commons Attribution-Noncommercial-No Derivative Works 4.0 License.
Document Type
Article - Conference proceedings
File Type
text
Language
English
Recommended Citation
Clemente, José L. M.; Davie, John R.; Nufer, Peter; and Anderson, Myron, "Micropiles for Support of Heavy Crane Ring Foundation" (2004). International Conference on Case Histories in Geotechnical Engineering. 20.
https://scholarsmine.mst.edu/icchge/5icchge/session01/20
Micropiles for Support of Heavy Crane Ring Foundation
New York, New York
The replacement of a steam generator at a nuclear power plant was accomplished with the use of a massive crane, believed to be one of the largest available cranes in the world market. Four steam generators were replaced, with each generator weighing 3.2 MN. The crane used for the job had a circular support that required a ring foundation. The crane support imposed huge loads on the ring foundation. Because of the presence of soft to medium stiff clayey fill on one side of the ring foundation, the load-sensitive nature of existing underground safetyrelated duct banks, and the nature of the loads applied to the foundation, it was necessary to support the ring foundation on piles. In order to minimize vibrations next to the containment building (the plant was operational while the piles were being installed), micropiles were selected. A total of 80 micropiles were installed, most of them at a batter of 10o from vertical, to provide the required vertical and lateral load resistance. Despite significant challenges imposed by space constraints, subsurface conditions, buried utilities, and design changes, the micropiles were installed within schedule, and performed as designed.