Location

Chicago, Illinois

Date

02 May 2013, 4:00 pm - 6:00 pm

Abstract

Artificial Ground Freezing was used to provide temporary earth support and groundwater control for a complex system of three frozen earth cofferdams for the Milwaukee Metropolitan Sewer District’s Harbor Siphons Project in Milwaukee, Wisconsin. Site geometry and frozen earth structural design precluded construction of one large excavation, requiring the component system of the tangential cofferdams. High groundwater velocity prevented the formation of the frozen earth walls during various stages of the project. Remedial methods including external dewatering, permeation grouting, jet grouting, timber shoring and sheet piling were attempted to complete the project. Ultimately a more aggressive ground freezing program was implemented and the project was successfully excavated. The design of the ground freezing system is presented, as well as the difficulties encountered with the high ground water velocity and its impact on freezing. The failed remedial approaches are discussed in detail, including lessons learned. A description of the aggressive ground freezing approach is included as it was the final solution to a complex problem of site geometry and unexpected groundwater conditions.

Department(s)

Civil, Architectural and Environmental Engineering

Meeting Name

7th Conference of the International Conference on Case Histories in Geotechnical Engineering

Publisher

Missouri University of Science and Technology

Document Version

Final Version

Rights

© 2013 Missouri University of Science and Technology, All rights reserved.

Creative Commons Licensing

Creative Commons License
This work is licensed under a Creative Commons Attribution-Noncommercial-No Derivative Works 4.0 License.

Document Type

Article - Conference proceedings

File Type

text

Language

English

Share

 
COinS
 
Apr 29th, 12:00 AM May 4th, 12:00 AM

Remediation of Distressed Frozen Earth Cofferdams

Chicago, Illinois

Artificial Ground Freezing was used to provide temporary earth support and groundwater control for a complex system of three frozen earth cofferdams for the Milwaukee Metropolitan Sewer District’s Harbor Siphons Project in Milwaukee, Wisconsin. Site geometry and frozen earth structural design precluded construction of one large excavation, requiring the component system of the tangential cofferdams. High groundwater velocity prevented the formation of the frozen earth walls during various stages of the project. Remedial methods including external dewatering, permeation grouting, jet grouting, timber shoring and sheet piling were attempted to complete the project. Ultimately a more aggressive ground freezing program was implemented and the project was successfully excavated. The design of the ground freezing system is presented, as well as the difficulties encountered with the high ground water velocity and its impact on freezing. The failed remedial approaches are discussed in detail, including lessons learned. A description of the aggressive ground freezing approach is included as it was the final solution to a complex problem of site geometry and unexpected groundwater conditions.