Location
Chicago, Illinois
Date
02 May 2013, 4:00 pm - 6:00 pm
Abstract
The Doha high-rise tower consists of a 4 level basement which required an excavation depth of 16m along the site perimeter. Minimization of impact of excavation-induced ground movements on the adjacent structures and underground utilities was one of the major considerations in the design and construction of the excavation and its temporary retaining system. The temporary retaining system initially consisted of anchored secant pile walls with toe grouting along the entire site perimeter. After excessive movement was detected on one section of the southern wall, inclined steel bracing was installed inside the excavation as a remedial measure to provide additional lateral support to the wall. This paper discusses the geotechnical aspects of the design and construction of the excavation and its retaining system, the analysis approaches employed to evaluate the conditions of the moving wall, and the remedial measures taken to prevent further wall movement.
Department(s)
Civil, Architectural and Environmental Engineering
Meeting Name
7th Conference of the International Conference on Case Histories in Geotechnical Engineering
Publisher
Missouri University of Science and Technology
Document Version
Final Version
Rights
© 2013 Missouri University of Science and Technology, All rights reserved.
Creative Commons Licensing
This work is licensed under a Creative Commons Attribution-Noncommercial-No Derivative Works 4.0 License.
Document Type
Article - Conference proceedings
File Type
text
Language
English
Recommended Citation
Chen, L. Tony, "A Case History of Deep Excavation in Doha" (2013). International Conference on Case Histories in Geotechnical Engineering. 2.
https://scholarsmine.mst.edu/icchge/7icchge/session03/2
A Case History of Deep Excavation in Doha
Chicago, Illinois
The Doha high-rise tower consists of a 4 level basement which required an excavation depth of 16m along the site perimeter. Minimization of impact of excavation-induced ground movements on the adjacent structures and underground utilities was one of the major considerations in the design and construction of the excavation and its temporary retaining system. The temporary retaining system initially consisted of anchored secant pile walls with toe grouting along the entire site perimeter. After excessive movement was detected on one section of the southern wall, inclined steel bracing was installed inside the excavation as a remedial measure to provide additional lateral support to the wall. This paper discusses the geotechnical aspects of the design and construction of the excavation and its retaining system, the analysis approaches employed to evaluate the conditions of the moving wall, and the remedial measures taken to prevent further wall movement.