Abstract
In this paper a case of foundation failure, due to which the complete bridge structure has collapsed, is considered. The bridge is situated in Km. 26/6 on Langi Durg Road. It was constructed in the year 1980-81. This bridge has two solid slab spans of 15.25 meters each. The substructure is of solid coarse rubble stone masonry. The base dimensions of pier foundation are 3780 mm. in traffic direction and 10080 mm. in current direction at R.L. 94.00m. The pier foundation is resting on bouldary strata. During the floods in the year 1995 the pier constructed in mid-stream failed. This brought down both the deck slabs of the bridge at the bed level. Both the deck slabs are in good condition and it is proposed to use them by lifting of slabs and reconstructing central pier after complete investigation of founding strata.
Department(s)
Civil, Architectural and Environmental Engineering
Meeting Name
4th Conference of the International Conference on Case Histories in Geotechnical Engineering
Publisher
University of Missouri--Rolla
Document Version
Final Version
Rights
© 1998 University of Missouri--Rolla, All rights reserved.
Creative Commons Licensing
This work is licensed under a Creative Commons Attribution-Noncommercial-No Derivative Works 4.0 License.
Document Type
Article - Conference proceedings
File Type
text
Language
English
Recommended Citation
Jain, J. K.; Saxena, A. K.; and Shrivastava, Sanjay Kumar, "Pier Failure of Bridge and Geotechnical Investigation − A Case Study" (1998). International Conference on Case Histories in Geotechnical Engineering. 11.
https://scholarsmine.mst.edu/icchge/4icchge/4icchge-session05/11
Pier Failure of Bridge and Geotechnical Investigation − A Case Study
St. Louis, Missouri
In this paper a case of foundation failure, due to which the complete bridge structure has collapsed, is considered. The bridge is situated in Km. 26/6 on Langi Durg Road. It was constructed in the year 1980-81. This bridge has two solid slab spans of 15.25 meters each. The substructure is of solid coarse rubble stone masonry. The base dimensions of pier foundation are 3780 mm. in traffic direction and 10080 mm. in current direction at R.L. 94.00m. The pier foundation is resting on bouldary strata. During the floods in the year 1995 the pier constructed in mid-stream failed. This brought down both the deck slabs of the bridge at the bed level. Both the deck slabs are in good condition and it is proposed to use them by lifting of slabs and reconstructing central pier after complete investigation of founding strata.