Settlement of a new reinforced concrete channel and related pipes was creatively underpinned and raised utilizing steel mini piles and compaction grout pile elements. The conditions that may have caused the settlement are systematically reviewed and details of construction are presented.

Department(s)

Civil, Architectural and Environmental Engineering

Meeting Name

3rd Conference of the International Conference on Case Histories in Geotechnical Engineering

Publisher

University of Missouri--Rolla

Document Version

Final Version

Rights

© 1993 University of Missouri--Rolla, All rights reserved.

Creative Commons Licensing

Creative Commons License
This work is licensed under a Creative Commons Attribution-Noncommercial-No Derivative Works 4.0 License.

Document Type

Article - Conference proceedings

File Type

text

Language

English

Share

 
COinS
 
Jun 1st, 12:00 AM

Underpinning and Leveling Settled Pipes and Channel

St. Louis, Missouri

Settlement of a new reinforced concrete channel and related pipes was creatively underpinned and raised utilizing steel mini piles and compaction grout pile elements. The conditions that may have caused the settlement are systematically reviewed and details of construction are presented.