Location
St. Louis, Missouri
Date
02 Jun 1993, 2:30 pm - 5:00 pm
Abstract
This report deals with problems connected with the design and construction of two levees built on thick soft compressible soils in the Po Delta. Settlement and pore pressure measurements in foundation soils, taken for about four years during and after construction by means of complete geotechnical instrumentation, were compared with results obtained through various methods during both design and back-analysis phases. Back-analysis was carried out using numerical simulations with finite-element programs. Considerations of the problems of the global stability of the embankments during the various construction phases are also presented.
Department(s)
Civil, Architectural and Environmental Engineering
Meeting Name
3rd Conference of the International Conference on Case Histories in Geotechnical Engineering
Publisher
University of Missouri--Rolla
Document Version
Final Version
Rights
© 1993 University of Missouri--Rolla, All rights reserved.
Creative Commons Licensing
This work is licensed under a Creative Commons Attribution-Noncommercial-No Derivative Works 4.0 License.
Document Type
Article - Conference proceedings
File Type
text
Language
English
Recommended Citation
Colleselli, F. and Cortellazzo, G., "Foundations for Large Embankments" (1993). International Conference on Case Histories in Geotechnical Engineering. 13.
https://scholarsmine.mst.edu/icchge/3icchge/3icchge-session02/13
Foundations for Large Embankments
St. Louis, Missouri
This report deals with problems connected with the design and construction of two levees built on thick soft compressible soils in the Po Delta. Settlement and pore pressure measurements in foundation soils, taken for about four years during and after construction by means of complete geotechnical instrumentation, were compared with results obtained through various methods during both design and back-analysis phases. Back-analysis was carried out using numerical simulations with finite-element programs. Considerations of the problems of the global stability of the embankments during the various construction phases are also presented.