A ten storeyed building, built on a subsoil of an onshore marine soil, was observed to be tilting away from the vertical. Extensive field and laboratory investigations were carried out to establish the reasons for the differential settlement causing the tilting. Though, nearly uniform pressure has been achieved at the foundation level, presence of a soft marine clay layer with varied thickness and location has caused the differential settlement. To arrest further increase in differential settlement, micropiling in the zone of higher settlement and additional loading and lowering of water table in the zone of lower settlement have been carried out as remedial measures. Controlled removal of the silty soil from below the foundation in the low settlement zone has reduced the differential settlement. The performance of the remedial measures has been monitored for more than two years.

Department(s)

Civil, Architectural and Environmental Engineering

Meeting Name

3rd Conference of the International Conference on Case Histories in Geotechnical Engineering

Publisher

University of Missouri--Rolla

Document Version

Final Version

Rights

© 1993 University of Missouri--Rolla, All rights reserved.

Creative Commons Licensing

Creative Commons License
This work is licensed under a Creative Commons Attribution-Noncommercial-No Derivative Works 4.0 License.

Document Type

Article - Conference proceedings

File Type

text

Language

English

Share

 
COinS
 
Jun 1st, 12:00 AM

Remedial Measures to a Building Settlement Problem

St. Louis, Missouri

A ten storeyed building, built on a subsoil of an onshore marine soil, was observed to be tilting away from the vertical. Extensive field and laboratory investigations were carried out to establish the reasons for the differential settlement causing the tilting. Though, nearly uniform pressure has been achieved at the foundation level, presence of a soft marine clay layer with varied thickness and location has caused the differential settlement. To arrest further increase in differential settlement, micropiling in the zone of higher settlement and additional loading and lowering of water table in the zone of lower settlement have been carried out as remedial measures. Controlled removal of the silty soil from below the foundation in the low settlement zone has reduced the differential settlement. The performance of the remedial measures has been monitored for more than two years.