Date
02 Jun 1988, 10:30 am - 3:00 pm
Abstract
At the Rocky Mountain Pumped Storage Project a 12 meter diameter power tunnel was excavated through sedimentary rock for 760 meters. Approximately 10% of this tunnel was through Pennington shale that is described as a dark gray massive organic shale. This paper will describe the methods of testing .and rock characterization, the results of instrumentation and monitoring, and the post-construction testing program for the excavation, and conclude with a discussion of the observed rock response in relation to the measured strength and deformation properties. This particular zone of the tunnel required the addition of longer rockbolts, and a discussion of that supplemental rock reinforcement will be included.
Department(s)
Civil, Architectural and Environmental Engineering
Meeting Name
2nd Conference of the International Conference on Case Histories in Geotechnical Engineering
Publisher
University of Missouri--Rolla
Document Version
Final Version
Rights
© 1988 University of Missouri--Rolla, All rights reserved.
Creative Commons Licensing
This work is licensed under a Creative Commons Attribution-Noncommercial-No Derivative Works 4.0 License.
Document Type
Article - Conference proceedings
File Type
text
Language
English
Recommended Citation
Prager, R. D.; Grainger, G. S.; and Butts, R. L., "Rock Response in a 12-M Tunnel through a Zone of Low Strength" (1988). International Conference on Case Histories in Geotechnical Engineering. 27.
https://scholarsmine.mst.edu/icchge/2icchge/2icchge-session2/27
Rock Response in a 12-M Tunnel through a Zone of Low Strength
At the Rocky Mountain Pumped Storage Project a 12 meter diameter power tunnel was excavated through sedimentary rock for 760 meters. Approximately 10% of this tunnel was through Pennington shale that is described as a dark gray massive organic shale. This paper will describe the methods of testing .and rock characterization, the results of instrumentation and monitoring, and the post-construction testing program for the excavation, and conclude with a discussion of the observed rock response in relation to the measured strength and deformation properties. This particular zone of the tunnel required the addition of longer rockbolts, and a discussion of that supplemental rock reinforcement will be included.