During the design phase of a 2000-towers electric power transmission line, a load test program was undertaken to evaluate the accuracy of new design methods for uplift and lateral capacity of drilled shafts. Seven uplift tests and six lateral load tests were performed in three different soil deposits: a medium clay, a very hard clay and a sand. The shafts were 2 ft in diameter and either 10 or 15 ft long. The pressuremeter test results are used together with existing methods to predict the behavior of the shafts.

Department(s)

Civil, Architectural and Environmental Engineering

Meeting Name

1st Conference of the International Conference on Case Histories in Geotechnical Engineering

Publisher

University of Missouri--Rolla

Document Version

Final Version

Rights

© 1984 University of Missouri--Rolla, All rights reserved.

Creative Commons Licensing

Creative Commons License
This work is licensed under a Creative Commons Attribution-Noncommercial-No Derivative Works 4.0 License.

Document Type

Article - Conference proceedings

File Type

text

Language

English

Share

 
COinS
 
May 6th, 12:00 AM

Power Line Foundation Design Using the Pressuremeter

During the design phase of a 2000-towers electric power transmission line, a load test program was undertaken to evaluate the accuracy of new design methods for uplift and lateral capacity of drilled shafts. Seven uplift tests and six lateral load tests were performed in three different soil deposits: a medium clay, a very hard clay and a sand. The shafts were 2 ft in diameter and either 10 or 15 ft long. The pressuremeter test results are used together with existing methods to predict the behavior of the shafts.