7. 3m high and 280 m long Manggar Besar homogeneous earthen dam resting on 12. 0 m thick soft silty clay, is under construction to supply water to the city of Balikpapan in Kalimantan island of Indonesia. To accelerate the anticipated 1. 6 m settlement of dam, 30 cm wide strip type drains (Colbond CX 1000) using polyester no-woven fabric are being used 3m centre to centre. It is expected that 70 percent consolidation shall take place within thirteen months of construction by these drains.

Department(s)

Civil, Architectural and Environmental Engineering

Appears In

International Conference on Case Histories in Geotechnical Engineering

Meeting Name

Second Conference

Publisher

University of Missouri--Rolla

Publication Date

6-1-1988

Document Version

Final Version

Rights

© 1988 University of Missouri--Rolla, All rights reserved.

Document Type

Article - Conference proceedings

File Type

text

Language

English

Share

 
COinS
 
Jun 1st, 12:00 AM

Colbond Drains for Rapid Consolidation at Manggar Besar Dam

7. 3m high and 280 m long Manggar Besar homogeneous earthen dam resting on 12. 0 m thick soft silty clay, is under construction to supply water to the city of Balikpapan in Kalimantan island of Indonesia. To accelerate the anticipated 1. 6 m settlement of dam, 30 cm wide strip type drains (Colbond CX 1000) using polyester no-woven fabric are being used 3m centre to centre. It is expected that 70 percent consolidation shall take place within thirteen months of construction by these drains.